12/16/2020

02:54 PM PIP II IT SSR1 Task #25327 (Assigned): SSR1 Resonance Controller Installation
Both RCCA and RCCB are both installed. Links between SOCMFC's and RCC's have been routed and connected. The spreads...

11/16/2020

03:01 PM PIP II IT SSR1 Task #24630: SSR1 Resonance Control chassis
Updated status of Resonance Controller Inventory. 2 more sent to SLAC, serial #'s 18061064 and 18060980

10/26/2020

03:20 PM PIP II IT SSR1 Task #24630: SSR1 Resonance Control chassis
Installed 1 Unit at CMTS in Relay Rack 201 for SSR1. Updated spreadsheet is attached.

10/06/2020

02:02 PM PIP II IT SSR1 Task #24630: SSR1 Resonance Control chassis
4 Resonance Controllers are being sent back to SLAC. See spreadsheet

10/01/2020

10:16 AM ANL Up/Down Converter Builds 2020/2021 Task #24853: Quotes and carts needed for Build of ANL Up/Downconverters

The attachment shows the purchase requisitions created.
Status of those PR:
37732 - Xometry - ordered and receive...
10:16 AM ANL Up/Down Converter Builds 2020/2021 1.00 hour (Task #24853 (New): Quotes and carts needed for Build of ANL Up/Downconverters)
Deleted Task#24854 on accident. This info was re entered from 9/28/20 and before.

09/29/2020

02:56 PM PIP-II IT Beam Pattern Generator Wiki edit: Wiki (#79)

09/21/2020

10:56 AM PIP-II IT Beam Pattern Generator Wiki edit: Wiki (#78)
10:39 AM PIP-II IT Beam Pattern Generator Wiki edit: Wiki (#77)
10:35 AM PIP-II IT Beam Pattern Generator Wiki edit: Wiki (#76)