02/18/2021

03:34 PM llrf-hwr-8cavity-firmware Revision 0a26d20c: Version 1.0.154, software 1.6.20, Labview 10-12-2020

01/26/2021

03:35 PM PIP-II IT HWR Bug #25437 (New): Simultaneous operation of Labview Screens
In the two cavity controllers of HWR and SSR1, when two Labview screens connected to
the same controller are opened...

12/17/2020

05:25 PM llrf-SSR1-2Cavity-firmware Revision 32f377e4: Detune data to RCC, Beam synch CW mode ver 1.0.118 - software 1.6.0, LV 10-12-20

12/15/2020

04:59 PM PIP II IT SSR1 Milestone #25216: Testing and Installing 2 RCC at CMTF
After a lot of work put in by the team, the first SSR1 cavity piezo tuner was successfully tested in closed loop.
It...
04:59 PM PIP II IT SSR1 4.00 hours (Milestone #25216 (Resolved): Testing and Installing 2 RCC at CMTF)
SSR1 Cavity 1 Piezo Tuner Testing

12/09/2020

10:59 AM PIP II IT SSR1 Milestone #25216: Testing and Installing 2 RCC at CMTF
The second SSR1 controller for cavity 3,4 was connected to the RCC and the link was tested
with the test waveform fr...
10:59 AM PIP II IT SSR1 4.00 hours (Milestone #25216 (Resolved): Testing and Installing 2 RCC at CMTF)
SSR1 controller 2 connection to RCC

12/07/2020

04:23 PM PIP II IT SSR1 Milestone #25216: Testing and Installing 2 RCC at CMTF
Controller 1 to the RCC fiber link has been successfully tested with a test waveform.
04:23 PM PIP II IT SSR1 4.00 hours (Milestone #25216 (Resolved): Testing and Installing 2 RCC at CMTF)
SSR1 controller 1 connected to Resonance Control Chassis at CMTF

11/19/2020

12:26 PM PIP II IT SSR1 Milestone #25216: Testing and Installing 2 RCC at CMTF
The FPGA configuration bit file update procedure was exercised successfully.
The listing of commands and messages is...