h1. Rack Power OFF procedures for planned power outages
2 56 David Caratelli
3 56 David Caratelli
*%{color:red}@Before a power-outage occurs@%*: alert Cryo engineers of planned MicroBooNE outages 1 week in advance.
4 1 Sowjanya Gollapinni
5 10 Sowjanya Gollapinni
*Who does this:* In the normal mode of operation, it is expected that ONLY sub-system experts (most probably on-call experts) will do the power off for their respective sub-systems. It is only in their absence and upon approval from the run coordinator that others will be allowed to do this.
6 1 Sowjanya Gollapinni
7 67 Sophie Berkman
*Step 0:* Go on the platform, with all requirements: Closed-toed shoes, and most importantly, Two-person rule!
8 10 Sowjanya Gollapinni
9 23 Sowjanya Gollapinni
h2. %{color:green}@Readout Electronics Racks Power-Off/On Procedure:@%
10 1 Sowjanya Gollapinni
11 10 Sowjanya Gollapinni
*Step 1:* Make sure the software DAQ/read-out processes are not running. In other words, this means that the platform power off procedure should ONLY be done AFTER the DAQ/read-out processes are brought down gracefully by the DAQ experts. Confirm from the On-call DAQ expert and the uB operator on shift that this is the case before proceeding.
12 3 Sowjanya Gollapinni
13 67 Sophie Berkman
*%{color:red}@Remember, the racks should be powered off in the following order, and following indicated steps.@%*
14 4 Sowjanya Gollapinni
15 2 Sowjanya Gollapinni
*Side note:* For reference, we are following the reverse of the prescription as written in
16 2 Sowjanya Gollapinni
 http://microboone-docdb.fnal.gov:8080/cgi-bin/RetrieveFile?docid=3825&filename=TPC-R1_Power-up.pdf&version=10 
17 2 Sowjanya Gollapinni
18 1 Sowjanya Gollapinni
*1. TPC-R2 through TPC-R5 power off:*
19 58 David Caratelli
0. Make sure DAQ is down.
20 1 Sowjanya Gollapinni
a. Switch off both Wiener PS using the red toggle switch on the front panel (gently push down the toggle switch for 3 seconds until the display turns off).
21 5 Sowjanya Gollapinni
b. Switch off the middle (CB2) and lowest (CB3) circuit breaker (circuit breaker switches have blue LEDs lit on them) by accessing the back side of the rack; verify fans are off.
22 68 Sophie Berkman
c.  Switch off top (CB1) circuit breaker; verify NetGear network switch inside rack is off. Look to see if lights on the top right side are off.
23 11 Sowjanya Gollapinni
d. Switch off Slow controls using front panel switch on the slow controls panel (gently pull the Chassis on/off switch and press down). The +5V, +3.3V, and Heart Beat LEDs should turn off.
24 68 Sophie Berkman
e. Switch off the RPS (use switch located on the back panel of the RPS unit). Go behind the racks and use a step stool to reach the switch, if needed. The switch is black and in the top right. Verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box, located at the bottom on the front of the rack, are off.
25 69 Sophie Berkman
f. Only the AC Input Good LED on the AC Switch Box, located at the bottom of the front of the rack, should be ON.
26 2 Sowjanya Gollapinni
27 2 Sowjanya Gollapinni
*2. TPC-R1 power off:*
28 58 David Caratelli
0. Make sure DAQ is down.
29 5 Sowjanya Gollapinni
a. Switch off Wiener PS using the red toggle switch on the front panel (gently push down the toggle switch for 3 seconds until the display turns off).
30 14 Sowjanya Gollapinni
b. Switch off the lowest (CB3) circuit breaker; verify fans are off.
31 14 Sowjanya Gollapinni
c. Switch off the middle (CB2) circuit breaker; verify NetGear network switch inside rack is off.
32 14 Sowjanya Gollapinni
d. Switch off Slow controls using front panel switch on the slow controls panel  (gently pull the Chassis on/off switch and press down). The +5V, +3.3V, and Heart Beat LEDs should turn off.
33 14 Sowjanya Gollapinni
e. Switch off the RPS (use switch located on the back panel of the RPS unit). Go behind the racks and use a step stool to reach, if needed; verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are off.
34 2 Sowjanya Gollapinni
f. Only the AC Input Good LED on the AC Switch Box should be ON.
35 2 Sowjanya Gollapinni
36 2 Sowjanya Gollapinni
*3. LIZ Rack power off:*
37 58 David Caratelli
0. Make sure DAQ is down.
38 2 Sowjanya Gollapinni
a. Switch off the two NIM bins using their front panel switches.
39 69 Sophie Berkman
b. Switch off the Tektronix function generator (Strobe pulser) using its front panel on/off button.
40 69 Sophie Berkman
c. Switch off the both fan switches on the fan front panels. The top fan is a green button, the lower one is a silver switch in the center. Verify the fans are off.
41 74 Sophie Berkman
d. Switch off the middle (CB2), top (CB1), and bottom (CB3) circuit breakers.Note: lights on the top two breakers are broken. 
42 11 Sowjanya Gollapinni
e. Switch off Slow controls using front panel switch on the slow controls panel  (gently pull the Chassis on/off switch and press down). The +5V, +3.3V, and Heart Beat LEDs should turn off.
43 5 Sowjanya Gollapinni
f. Switch off the RPS (use switch located on the back panel of the RPS unit). Go behind the racks and use a step stool to reach, if needed; verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are off.
44 1 Sowjanya Gollapinni
g. Only the AC Input Good LED on the AC Switch Box should be ON.
45 2 Sowjanya Gollapinni
46 5 Sowjanya Gollapinni
*4. PMT/TRIG Rack power off:*
47 59 David Caratelli
48 59 David Caratelli
49 69 Sophie Berkman
*%{color:red}@First confirm from the On-call PMT expert and uB operator on shift that the PMT HV is ramped down as per procedure and is at 0 V. Do not proceed without this confirmation. This can be checked on the front of the PMT rack.@%*
50 59 David Caratelli
51 59 David Caratelli
0. Make sure DAQ is down.
52 69 Sophie Berkman
a. Switch off Wiener PS using the red toggle switch on the front panel (gently push down the toggle switch for 3 seconds until the display turns off). There is one for both the PMT and trigger.
53 74 Sophie Berkman
b. Switch off the NIM bin using its front panel switch. (Note: light is broken on the front of the trigger NIM crate power supply.)
54 70 Sophie Berkman
c. Check that the PMT HV (CB3) bottom circuit breaker is off. If not, stop and call a PMT HV expert.
55 28 Jeremy Hewes
d. Switch off the fan underneath the trigger NIM bin. 
56 69 Sophie Berkman
e. Switch off the middle (CB2) circuit breaker; verify the fan is off. (Note: LED on CB2 is broken.)
57 28 Jeremy Hewes
f. Switch off the CB1 circuit breaker; verify NetGear network switch inside rack is off.
58 28 Jeremy Hewes
g. Switch off Slow controls using front panel switch on the slow controls panel  (gently pull the Chassis on/off switch and press down). The +5V, +3.3V, and Heart Beat LEDs should turn off.
59 28 Jeremy Hewes
h. Switch off the RPS (use switch located on the back panel of the RPS unit). Go behind the racks and use a step stool to reach, if needed; verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are off.
60 28 Jeremy Hewes
i. Only the AC Input Good LED on the AC Switch Box should be ON.
61 2 Sowjanya Gollapinni
62 14 Sowjanya Gollapinni
5. Make an elog entry that the readout electronics racks have been successfully powered off.
63 6 Sowjanya Gollapinni
64 23 Sowjanya Gollapinni
h2. %{color:green}@DRIFT HV rack Power-Off/On procedure:@%
65 1 Sowjanya Gollapinni
66 20 Sowjanya Gollapinni
*%{color:red}@First confirm from the On-call Drift HV expert and uB operator on shift that the DRIFT HV is ramped down as per procedure and is at 0 V. Do not proceed without this confirmation.@%*
67 1 Sowjanya Gollapinni
68 1 Sowjanya Gollapinni
Step 1: After confirming the above, ensure that the Glassman is at 0 V by looking at the power supply front panel. If the power happens to be off, the voltage is 0. 
69 1 Sowjanya Gollapinni
(At this point, if a power outage occurs, it is ok from a HV health standpoint.  The remaining steps are additions for a more graceful shutdown of the entire HV rack.)
70 1 Sowjanya Gollapinni
71 1 Sowjanya Gollapinni
a. After confirming Step 1, turn off the Glassman by pushing the orange on/off button on the front of the supply.
72 1 Sowjanya Gollapinni
b. Turn off the slow controls box by gently pulling the on/off switch on the front left side of the box and pushing it down. The +5V, +3.3V, and RPS Status LEDs should turn off.
73 1 Sowjanya Gollapinni
c. Switch off the RPS (use switch located on the back panel of the RPS unit). Go behind the racks and use a step stool to reach, if needed; verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are off.
74 1 Sowjanya Gollapinni
f. Only the AC Input Good LED on the AC Switch Box should be ON.
75 1 Sowjanya Gollapinni
76 1 Sowjanya Gollapinni
Once done, let the uB operator on shift know that the power-off is done and make an e-log entry that the rack has been successfully powered off.
77 14 Sowjanya Gollapinni
78 23 Sowjanya Gollapinni
h2. %{color:green}@ZMON box Power-Off/On procedure:@%
79 14 Sowjanya Gollapinni
80 1 Sowjanya Gollapinni
a. The ZMON unit is located separately on a single shelf next to the PM01 rack. Turn off the ZMON slow controls box by gently pulling the on/off switch on the front left side of the box and pushing it down.
81 1 Sowjanya Gollapinni
82 21 Sowjanya Gollapinni
Once done, let the uB operator on shift know that the power-off is done and make an e-log entry that the rack has been successfully powered off.
83 21 Sowjanya Gollapinni
84 23 Sowjanya Gollapinni
h2. %{color:green}@TPC-PS (subsystem: OnDetPower) rack Power-Off/On procedure:@%
85 14 Sowjanya Gollapinni
86 19 Sowjanya Gollapinni
*%{color:red}@The TPC-PS rack power down CANNOT be done until the TPCPS expert has gracefully brought all channels down and turned them off including the Power supply Main Switch. First confirm from the uB operators on shift that this has been done. Once confirmed, proceed with the steps below.@%*
87 14 Sowjanya Gollapinni
88 14 Sowjanya Gollapinni
a. Switch off the Wiener MPOD power supply (located on the bottom portion of the rack) by pressing the front panel ON/OFF switch. The front panel display should turn off.
89 1 Sowjanya Gollapinni
b. Switch off the Calibration Pulsar (needs picture and location in the rack)
90 14 Sowjanya Gollapinni
c. Turn off the Slow controls box (second box from top). Slightly (and gently) pull the Chasis ON/OFF switch and press down. All LEDs should come down.
91 1 Sowjanya Gollapinni
d. Now, go to the back side of the rack, and open the back door of the rack and power off the RPS ON/OFF switch located on the back panel of the RPS box (Top most box in the rack). Use step stool if needed to reach the switch.
92 21 Sowjanya Gollapinni
e. Flip all the Eaton breaker switches down (Eaton breaker switches are located on the right side of each rack with blue lights lit. There are 3 Eaton switches per rack).
93 14 Sowjanya Gollapinni
94 21 Sowjanya Gollapinni
Once done, let the uB operator on shift know that the power-off is done and make an e-log entry that the rack has been successfully powered off.
95 21 Sowjanya Gollapinni
96 1 Sowjanya Gollapinni
h2. %{color:green}@Purity Monitor (PM01, PM02, PM03) rack Power-Off/On procedure:@%
97 14 Sowjanya Gollapinni
98 60 David Caratelli
+*%{color:red}NOTE: Currently the Purity Monitor is NOT Being Used. Do not power back up these racks.%*+
99 50 Kevin Wierman
100 29 Ben Carls
h3. Power-off
101 29 Ben Carls
102 29 Ben Carls
# Locate the three racks, which are on the platform. They are PM-R1, PM-R2, and PM-R3.
103 29 Ben Carls
# Turn off the NIM bins in each rack by moving the switch labeled "ON/OFF" to "OFF". If the NIM bin’s power light goes off, you were successful in turning the NIM bin off. If the light stays on, try moving the switch once more.
104 29 Ben Carls
# Each rack has a Windows server in it. Turn off the PCs by holding down their power buttons (yes, I know). This is the most secure way to turn off the Windows PCs as it does not involve actually logging into the system.
105 29 Ben Carls
# Turn off the Slow Controls box by flipping the switch on its front panel to the OFF position. 
106 29 Ben Carls
# Go to the back of the rack and turn off the RPS box using the switch located on its back. 
107 29 Ben Carls
# The rack can now be powered-off without causing harm. On the Surge-X power strips located in the top of each rack, press down on the "OFF" portion of the "ON/OFF" button.
108 29 Ben Carls
109 21 Sowjanya Gollapinni
Once done, let the uB operator on shift know that the power-off is done and make an e-log entry that the rack has been successfully powered off.
110 29 Ben Carls
111 29 Ben Carls
h3. Power-on
112 29 Ben Carls
113 29 Ben Carls
# Locate the three racks, which are on the platform. They are PM-R1, PM-R2, and PM-R3.
114 29 Ben Carls
# Give the rack electricity by pressing down on the "ON" portion of the "ON/OFF" button on the Surge-X power strip. 
115 29 Ben Carls
# Go to the back of the rack and turn on the RPS box using the switch located on its back. 
116 29 Ben Carls
# Turn on the Slow Controls box by flipping the switch on its front panel to the ON position. 
117 29 Ben Carls
# Turn on the NIM bins in each rack.  This is accomplished by doing the opposite of the turn off procedure. Move the "ON/OFF" switch to the "ON" position to turn on the NIM bin.
118 29 Ben Carls
# Each rack has a Windows server in it. Turn on the PCs by pressing down their power buttons. Allow the disk check to proceed since we turned off the PC in such a hard fashion as described above.
119 29 Ben Carls
# The flash-lamps in PM-R1 and PM-R2 will need to be set to run again. To do this, take the clear LEXAN™ sheet off of the front of the rack. You’ll need a flathead screwdriver to accomplish this (if you can fit your hand in underneath the LEXAN™ sheet to get to the power supply panel, do that instead). Once that has been removed, open up the brass screen on the front of the Faraday cage. There are two screws for this on the top edge of the brass screen. The front of the flash-lamp power-supply will now be visible. Look for the white, square button labeled "RUN". Press that button. You should see a little, red light next to it. That means your pressing of the button was successful and you wont need to run off with the circus. 
120 29 Ben Carls
# If the Windows servers are back online, call the purity monitor expert on call to turn the purity monitor DAQ on. They will do it remotely.
121 29 Ben Carls
122 29 Ben Carls
h3. Power-on issues
123 29 Ben Carls
124 30 Ben Carls
There are two potential issues with turning the purity monitors back on. You will be notified and walked through the procedures below by the purity monitor expert if they are needed. 
125 30 Ben Carls
126 29 Ben Carls
Firstly, the network on the Windows servers sometimes does not come back after startup. The purity monitor expert on call will confirm if this has happened. To fix this, simply unplug the network cable on the back of the server, wait 10 seconds (I suppose it should be a minute to conform to standard troubleshooting procedures, but we're not that patient), and plug it back in. 
127 29 Ben Carls
128 32 Xiao Luo
Secondly, the flash-lamp power supply can sometimes come back in a funny state that does not allow it to run. One of the error message related to this issue is "Error: Capture timeout of the noise data after 300000 ms -- verify trigger 0". This means the flash-lamp can not fire. Here are the instructions on resetting it. -It unfortunately involves taking the side of the rack off and opening up the faraday cage-. If you do this, you must not do anything to alter the alignment of the flash-lamp housing or the fiber going into it. The purity monitor signals are highly sensitive to fiber-lamp alignment. 
129 29 Ben Carls
130 29 Ben Carls
# Power unit off.
131 29 Ben Carls
# Power unit on with run function off (don't run the DAQ program or have the electronics module on "Local"). You really don't need to worry about this step. 
132 29 Ben Carls
# Set for frequency display.
133 29 Ben Carls
# Set frequency down to 0.1 Hz.
134 29 Ben Carls
# Set frequency up to 75 Hz.
135 29 Ben Carls
# Set frequency to desired repetition rate, we use 2 Hz.
136 29 Ben Carls
# Now set the energy level, we use 5,000 mJ.
137 29 Ben Carls
138 23 Sowjanya Gollapinni
h2. %{color:green}@LASER racks Power-Off/On procedure:@%
139 19 Sowjanya Gollapinni
140 54 Thomas Strauss
*%{color:red}@First inform from the LASER experts (Michele Weber, Igor Kreslo, Thomas Strauss). They will ensure that the LASER is off and the Laser computers that are in the rack are also gracefully brought down. Do not proceed without this confirmation.@%*
141 25 Matthias Luethi
Turning off devices in the rack:
142 27 Matthias Luethi
1. Contact a laser expert, who will tell you where you can find the key to open the laser racks.
143 71 Sophie Berkman
2. Turn off the main switch of the laser power supply on the front (different from the key). Note: Usually off when not taking laser data.
144 71 Sophie Berkman
3. Turn off the NIM crate power. Note: Usually off when not taking laser data.
145 72 Sophie Berkman
4. Turn off the server if they are still running (Button is in the very right upper corner, under UPS). %{color:red}@Usually on@%
146 27 Matthias Luethi
5. Open the laser racks on the back:
147 72 Sophie Berkman
6. Turn all switches to the off state on all devices (T-OMG1, T-OMG2, Aperture, Attenuator etc. ) on the power supply box (located about 1m above ground). Note: Usually off when not taking laser data.
148 72 Sophie Berkman
7. Turn off the main switch of the device power supply box (located on the back of the box). Note: Usually off when not taking laser data.
149 72 Sophie Berkman
8. Turn off the power of the Thermionics motor control unit (blue box, switch is located on the front). Note: Usually off when not taking laser data.
150 72 Sophie Berkman
9. Turn off the power of the Heidenhain encoder control unit (grey box, switch is located next to the power cable in the back of the device). Note: Usually off when not taking laser data.
151 72 Sophie Berkman
10. Turn off the power supply of the fans in the laser enclosure (lower metallic box), switch is located in the upper left corner. Note: Usually off when not taking laser data.
152 1 Sowjanya Gollapinni
153 1 Sowjanya Gollapinni
Turning off slow controls
154 1 Sowjanya Gollapinni
a. Turn off the slow controls box by gently pulling the on/off switch on the front left side of the box and pushing it down. The +5V, +3.3V, and RPS Status LEDs should turn off.
155 1 Sowjanya Gollapinni
b. Switch off the RPS (use switch located on the back panel of the RPS unit). Go behind the racks and use a step stool to reach, if needed; verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are off.
156 1 Sowjanya Gollapinni
c. Only the AC Input Good LED on the AC Switch Box should be ON.
157 1 Sowjanya Gollapinni
158 73 Sophie Berkman
11. Turn off UPS. %{color:red}@Usually on@%
159 72 Sophie Berkman
160 1 Sowjanya Gollapinni
Once done, let the uB operator on shift know that the power-off is done and make an e-log entry that the rack has been successfully powered off.
161 1 Sowjanya Gollapinni
162 1 Sowjanya Gollapinni
Power on:
163 72 Sophie Berkman
1. Turn on slow controls.
164 72 Sophie Berkman
2. On both UPSes in the rack, unplug the cable with the label "EPO" (this will make it possible to power on the UPS).
165 72 Sophie Berkman
3. Power on the lower UPS first, followed by the upper UPS.
166 72 Sophie Berkman
4. Turn on the Rack Protection System (located at the top of the rack and switch in the back).
167 72 Sophie Berkman
5. The UPS should switch from battery mode to external power within few seconds.
168 1 Sowjanya Gollapinni
6. Plug EPO cable back in.
169 73 Sophie Berkman
7. Turn on all of the devices above in reverse order. If not taking laser runs, only power up devices that are usually on.
170 72 Sophie Berkman
CAUTION: *Do not turn on the green alignment laser*. This is the switch on the silver panel in the back labeled A-Laser!. It should have a tape to cover it in the closed position. If that is missing, call Thomas/Michele/Igor.
171 75 Sophie Berkman
8. Big green button on front of laser racks is usually on; turn it on if it is not already.
172 75 Sophie Berkman
9. Make an elog that rack has been successfully powered on.
173 72 Sophie Berkman
174 72 Sophie Berkman
-After turning on slow controls: On both UPS in the rack, unplug the cable with the label EPO (this will allow to power on the UPS). Then power on the lower UPS first, followed by the upper UPS. Turn on the Rack Protection System (located at the top of the rack and switch in the back). The UPS should switch from battery mode to external power within few seconds. After this power up the devices in reverse order (as described above). Between step 3 and 4, plug back in the EPO cable. CAUTION: *Do not turn on the green alignment laser*. This is the switch on the silver panel in the back labeled A-Laser!. It should have a tape to cover it in the closed position. If that is missing, call Thomas/Michele/Igor.-
175 1 Sowjanya Gollapinni
176 49 Rui An
h2. %{color:green}@ MuCS (Muon Counter System) rack Power-Off/On procedure:@%
177 33 Matthew Bass
178 33 Matthew Bass
h2. Powering down the system
179 33 Matthew Bass
180 49 Rui An
To power off the MuCS rack the following steps should be followed by a MuCS expert:
181 63 Rui An
# Set switches on the HV PS to "off" (NOT the "kill") to ramp down the HV for the PMTs. 
182 63 Rui An
# Switch off the LV power supply by pressing (1)the output button (2)On/off button in the LV power supply.
183 33 Matthew Bass
# Shut down the laptop.
184 33 Matthew Bass
# Open rear door and flip the power switch on the RPS to the off position (looking from the back of the rack it's at the top right).
185 33 Matthew Bass
# Power off the SurgeX by flipping the switch on the front of the rack.
186 33 Matthew Bass
187 33 Matthew Bass
h2. Powering on the system
188 33 Matthew Bass
189 57 David Caratelli
To power on the MuCS rack the following steps should be followed by a MuCS expert:
190 33 Matthew Bass
# Power on the SurgeX.
191 33 Matthew Bass
# Open rear door and power on the RPS.
192 34 Matthew Bass
# Power on the laptop. Make sure it boots and logs into the the dcdaq account. Should do so automatically, if not log into that account.  This will start a vnc server so that experts can access the machine remotely.
193 33 Matthew Bass
# Turn on the LV. This required both turning on the LV PS and turning on the LV power output. There is a light on the LV PS to indicate if LV is on as well as three LEDs on the front banana plugs to indicate that the LV is on.
194 33 Matthew Bass
# Once the LV is confirmed to be on (LED lights are on) then the HV can be turned on by setting the switches on the HV supply to the "on" (up) position.
195 33 Matthew Bass
# After a reset, you should take a test run (use Ghost mode) to ensure that triggers are coming out unprescaled (top counter) and prescaled (bottom counter). Often the prescaled triggers do not come through and the prescaler has to be reset. To reset the prescaler (second trigger module from left, labeled "Trigger Divider"), set the top counter to 000 and then back to 100 (the nominal prescale factor for MuCS triggers).
196 35 Rui An
197 35 Rui An
h2. %{color:green}@ CRT (Cosmic Ray Tagger) rack Power-Off/On procedure:@%
198 38 Rui An
199 38 Rui An
*Power OFF:*
200 38 Rui An
201 39 Rui An
%{color:red}Before powering off the racks, please refer to the link below to turn off CRT DAQ and bias:
202 39 Rui An
https://cdcvs.fnal.gov/redmine/projects/uboone-operations/wiki/Cosmic_Ray_Tagger_-_Experts_Only%
203 37 Rui An
204 37 Rui An
There are three racks for CRT. They are CRT-DAQ-R1, CRT-DAQ-R2 and CRT-Utility racks.
205 37 Rui An
206 37 Rui An
CRT-DAQ-R1 rack power off:
207 37 Rui An
# Make sure turn off the servers following descriptions in link above. Do NOT use the on/off button which is brutal.
208 1 Sowjanya Gollapinni
# Turn off slow control box(use switch on the front). The +5V, +3.3V, and Heart Beat LEDs should turn off.
209 46 Rui An
# Turn off UPS use its power button. Press the button for about 3 seconds until the green light if off.
210 37 Rui An
# Turn off RPS(use switch on the back). Verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are off.
211 37 Rui An
# Now rack is off and  only the AC Input Good LED on the AC Switch Box should be ON. 
212 37 Rui An
213 37 Rui An
CRT-DAQ-R2 rack power off:
214 37 Rui An
# Make sure turn off the servers following descriptions in link above. Do NOT use the on/off button which is brutal.
215 1 Sowjanya Gollapinni
# Turn off slow control box(use switch on the front). The +5V, +3.3V, and Heart Beat LEDs should turn off.
216 46 Rui An
# Turn off UPS use its power button. Press the button for about 3 seconds until the green light if off.
217 37 Rui An
# Turn off RPS(use switch on the back). Verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are off.
218 37 Rui An
# Now rack is off and  only the AC Input Good LED on the AC Switch Box should be ON. 
219 37 Rui An
220 37 Rui An
CRT-Utility rack power off:
221 1 Sowjanya Gollapinni
# Turn off Wiener PS channel-wisely using slow monitoring which is also described in the link above. If you can not figure it out, go to item (2).
222 44 Rui An
# Turn off Wiener PS channel-wisely using the switch on the front. If you can not figure it out, go to item (1)...sorry, call expert then.
223 39 Rui An
# Turn off Wiener PS using the red toggle switch on the front panel (gently push down the toggle switch for 3 seconds until the display turns off).
224 1 Sowjanya Gollapinni
# Turn off the NIM crate and its fan(use switch in the front). These two are now put in 'OFF' state.
225 39 Rui An
# Turn off PPS(use switch on the front). Check the blinking blue light is off.
226 1 Sowjanya Gollapinni
# Turn off slow control box(use switch on the front). The +5V, +3.3V, and Heart Beat LEDs should turn off.
227 1 Sowjanya Gollapinni
# Turn off RPS(use switch on the back). Verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are off.
228 39 Rui An
# Turn off the Surge X(use switch on the front). Verify the power light is off.
229 39 Rui An
230 45 David Martinez
Once done, let the uB operator on shift know that the power-off is done and make an e-log entry that the rack has been successfully powered off.
231 45 David Martinez
232 40 Rui An
*Power On:*
233 39 Rui An
234 66 Rui An
Please power on R2 first which has the network switch .
235 44 Rui An
236 66 Rui An
CRT-DAQ-R2 rack power on:
237 42 Rui An
# Check the AC Input Good LED on the AC Switch Box is ON.
238 1 Sowjanya Gollapinni
# Turn on RPS. Verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are on.
239 43 Rui An
# Turn on UPS by the power button on the front. Hold the power button for about 3 seconds. It can take up to minutes for the UPS to warm up.
240 65 Rui An
# Wait some time for the network switch to work
241 1 Sowjanya Gollapinni
# Turn on slow control box(use switch on the front). The +5V, +3.3V, and Heart Beat LEDs should turn on.
242 64 Rui An
# Check the power light of network switch the front is on.
243 1 Sowjanya Gollapinni
# Turn on the servers(use red button on the front).
244 1 Sowjanya Gollapinni
245 66 Rui An
CRT-DAQ-R1 rack power on:
246 1 Sowjanya Gollapinni
# Check the AC Input Good LED on the AC Switch Box is ON.
247 1 Sowjanya Gollapinni
# Turn on RPS. Verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are on.
248 1 Sowjanya Gollapinni
# Turn on UPS by the power button on the front. Hold the power button for about 3 seconds. It can take up to minutes for the UPS to warm up.
249 1 Sowjanya Gollapinni
# Turn on slow control box(use switch on the front). The +5V, +3.3V, and Heart Beat LEDs should turn on.
250 76 Sophie Berkman
# Turn on the servers(use red button on the front). (Note: Usually turn on themselves. Contact CRT expert if they do not.)
251 64 Rui An
252 64 Rui An
253 64 Rui An
CRT-Utility rack power on:
254 64 Rui An
# Turn on the Surge X(use switch on the front). Verify the power light is on.
255 64 Rui An
# Turn on RPS. Verify the AC Output ON, POWER, SENSOR, and ALARM LEDs on the AC Switch Box are on.
256 64 Rui An
# Turn on slow control box(use switch on the front). The +5V, +3.3V, and Heart Beat LEDs should turn on.
257 64 Rui An
# Turn on PPS. Check the blue blinking light is on.
258 76 Sophie Berkman
# If you need the NIM, turn on the NIM crate and its fan(use switch in the front). (Note: Usually off) 
259 64 Rui An
# Turn on Wiener PS use the red toggle switch
260 76 Sophie Berkman
# Turn on Wiener PS channel-wisely using the switch on the front. If you can not figure it out, go to item (8). (Note: done remotely)
261 76 Sophie Berkman
# Turn on Wiener PS channel-wisely using slow monitoring which is also described in the link above. If you can not figure it out, call expert. (Note: done remotely)
262 1 Sowjanya Gollapinni
263 1 Sowjanya Gollapinni
After powering on the racks, please refer to the link below to turn on CRT DAQ and bias:
264 41 Rui An
https://cdcvs.fnal.gov/redmine/projects/uboone-operations/wiki/Cosmic_Ray_Tagger_-_Experts_Only
265 1 Sowjanya Gollapinni
266 1 Sowjanya Gollapinni
*Make an e-log entry after successfully turning off/ on the system.*