Project

General

Profile

Expert - Power up procedure

After a power outage, there will be dedicated steps to turn on the rack. Make sure, the pwoer strip in the back is turned on. Disconnect the EPO input on the UPS, to start the UPS, which than will power the RPS. Afterwards, connect the EPO input again. Check that all items are turned back on now (e.g. NIM bin + fan, slow control monitor, server!). Never start the server, when the evb is still down, as it mounts from this mashine!