04182014 Minutes

Attending Michael, Gavin, Evan, Mat

Far Milestones List
Milestone Date Run Number Comments
Partition 1 Running DB 1-7 April 14, 2014 14702
Full detector running (9 diblocks with APDs, 4 without APDs) April 4-7 14563-14594
Partition 1 gets diblock 4 March 11, 2014 13800
Partition 1 gets diblock 3 February 17, 2014 13197
TDU Timing calibration February 3, 2014 12885
Established partition 1 as stable partion Janurary 31, 2014 On this date the definitions of the 3 partitions was established. Initially db 1-3 were included and later reduced to diblock 1-2 on Feb 2.
Thresholds lowered December 3, 2013 11823 ~4 sigma
Cold Full Gain Unmangled data Oct 25, 2013 11496 Use data prior to this at your own risk.