Period and Epoch Naming

Period Epoch Detector Run # Beamline Run # Analysis / Comments
Commissioning
Friday March 22 2019
Period 1 Epoch 1a - 2500 First beamline data collected with beam. Mostly just junk data as things were timed in and set up.
- 2847
Monday June 3 2019
Epoch 1b 100023 2849 First analysis-quality beamline data. First beam data with operating detector.
100191 3001
Wednesday July 3 2019
Epoch 1c 100192 3002 Changed timing in of the beamline trigger signal.
100218 3029
Summer 2019 Shutdown: Saturday July 6 2019
Thursday December 5 2019
Period 2 Epoch 2a 100224 3064 First beam data after shutdown. FD FEB firmware (v4.10.2E); various triggers, mostly DS-ToF.
100499 3272
Thursday January 16 2020
Epoch 2b 100500 3273 FEB firmware 4.11.30; ToFPrompt trigger.
100523 3285
Thursday January 23 2020
Epoch 2c 100524 3286 Trigger study period, mostly involving paddles; FEB firmware 4.11.30.
100674 3411
Saturday February 15 2020
Epoch 2d 100675 3412 FEB firmware 4.11.30; 4-of-4 paddle trigger.
100698 3417
Tuesday February 18 2020
Epoch 2e 100699 3417 FEB firmware 4.11.33; 4-of-4 paddle trigger.
100791 3470
Thursday March 5 2020
Epoch 2f 100792 3470 FD FEB firmware (v4.10.2E); 4-of-4 paddle trigger.
100856 3503
COVID-19 Shutdown: Friday March 20 2020
Tuesday January 12 2021
Period 3 Epoch 3a 100985 3622 First beam data after shutdown.

 

There were a few runs that with a warm detector from firmware testing. The list of them can be found here: https://cdcvs.fnal.gov/redmine/projects/novatestbeam/wiki/Commissioning_runs#DETECTOR-DATA