Commissioning runs

Below is a running list of commissioning runs.

UP TO DATE AS OF 2019-05-10

Start Date | Run   | Num. files | Trigger Pattern                | Current | Notes
-----------+-------+------------+--------------------------------+---------+---------------------------------------------
2019-05-04 | 2729  | 10         | WC scintillator panels         | 1000 A? | Run ended with beam off due to klystron
           |       |            |                                |         | issues at Linac.
-----------+-------+------------+--------------------------------+---------+---------------------------------------------
2019-05-05 | 2730  | 16         | WC scintillator panels         | 1000 A? | Magnet current readout issues begun. Beam 
           |       |            |                                |         | downtime at end of run.
-----------+-------+------------+--------------------------------+---------+---------------------------------------------
2019-05-06 | 2733  | 4          | WC scintillator panels         | 1000 A? |
           |       |            |                                |         |
-----------+-------+------------+--------------------------------+---------+---------------------------------------------
2019-05-06 | 2734  | 2          | WC scintillator panels         | 2000 A  | Test at 2000 A 
           |       |            |                                |         | 
-----------+-------+------------+--------------------------------+---------+---------------------------------------------
2019-05-06 | 2735  | 7          | WC scintillator panels         | 500 A   | Test at 500 A (M1 Ref)
           |       |            |                                |         | 
-----------+-------+------------+--------------------------------+---------+---------------------------------------------