NDOS Commissioning Meeting 2012/01/12

Attendance: Jon, Andrew, Gavin, Raphael, Leon, Susan, Nick, Minerba,

Agenda:

  1. Beam and Detector Update
  2. Installation Plans for the next week
  3. DAQ Update and Plans for next week
  4. DCS Update and Plans for next week
  5. AOB

Beam and Detector Report

  • Nothing major to report,

Installation plans for next week

  • None.

DAQ Update and Plans for next week

  • Peter: did some tests of the Message Analyzer; it kinda works, but needs some tuning. Didn't give the same results as the checksync script, but further tests/debugging will continue. Further DDS tests will continue.

DCS Update and Plans for next week

  • Athans: Nothing in particular to report.