04-Oct-2010, KAB - The purpose of this page is to keep track of requests that we want to send to Mark Bowden for changes to the official WBS.

Early October (2010) list:
  1. Move System Integration & Test later in the list. With this change, the L3 Trigger and DAQ WBS entries will be the following:
    • 475.09.01 Project Management
    • 475.09.02 System Design & Development Infrastructure
    • 475.09.03 Data Acquisition
    • 475.09.04 Data Processing
    • 475.09.05 Controls & Networking
    • 475.09.06 System Integration & Test
  2. Remove the following L5 items:
    • System Integration & Test / Software / Preliminary Design
    • System Integration & Test / Software / Trigger Prototype System
  3. Add the following L5 items (between DAQ Pilot System and Production System):
    • System Design & Development Infrastructure / Software / Integrated Pilot System
    • Data Acquisition / Software / Integrated Pilot System
    • Data Processing / Software / Integrated Pilot System
    • Controls & Networking / Software / Integrated Pilot System
    • System Integration & Test / Software / Integrated Pilot System