Bi-weekly Meeting Minutes:

- Tomo working to add debug packets to overlay. Posted update to packet definition doc in DocDB. And is starting to follow discussions with Rob.
- Glenn following developments at Brookhaven regarding web-based GUI for EPICS. Wants to get DCS stuff going on Mu2e Pilot system computers.
- Rick working on getting a stable DTC firmware release.
- Eric and Ryan working with Vadim to get the most of out of radiation hardness tests for ROC in two weeks.
- Eric created artdaq plug-in for epics/ganglia monitoring.

Clock Discussion:

<see attached image>

Action Items:
- Bring up rack safety requirements with safety people.
- Periodically distribute current TDAQ schedule to our group.