h1. Daily check list
2 1 Marc testing Mengel
3 1 Marc testing Mengel
h2. Before 2pm
4 6 Thomas Diehl
5 5 Thomas Diehl
# Perform End Of Night Checklist in the logbook if the observers didn't do it.
6 19 Thomas Diehl
# Write the Synopsis_Night logbook entry if the observers didn't do it.
7 5 Thomas Diehl
# Publish the nightsum in the morning if the observers didn't do it.
8 5 Thomas Diehl
# Complete CTIO end of night report if the observers didn't do it.
9 5 Thomas Diehl
# Be aware of our observers arrival to and departure from the mountain. 
10 1 Marc testing Mengel
# Prepare the nightly plan page, including populating Almanac and Weather info
11 1 Marc testing Mengel
# Check the instrument status (read the logbook, talk to people)
12 1 Marc testing Mengel
# Check the DM status
13 1 Marc testing Mengel
# Check SISPI status 
14 17 Klaus Honscheid
# Check what scripts are needed/present for calibration
15 17 Klaus Honscheid
# "Take a first look at the DESDM data quality results":https://cdcvs.fnal.gov/redmine/projects/desops/wiki/DM_into_Database 
16 17 Klaus Honscheid
Only fetch the data and check if there is anything unusual that should be discussed at the 4pm meeting. 
17 4 Thomas Diehl
# Send out the agenda for the 4pm meeting (if to occur) to des_observers@fnal.gov
18 9 Stephen Kent
# Check diskspace.  Log into one of the observer machines as user "sispi"
19 4 Thomas Diehl
<pre>
20 4 Thomas Diehl
setup SISPI
21 4 Thomas Diehl
check_diskspace
22 4 Thomas Diehl
</pre>
23 4 Thomas Diehl
If any disks are filling up (>90% for observer2, >93% for the pipeline
24 8 Stephen Kent
machines) send an email to Klaus and Ann (kh@physics.osu.edu and
25 8 Stephen Kent
elliotta@mps.ohio-state.edu)
26 4 Thomas Diehl
27 1 Marc testing Mengel
28 2 Thomas Diehl
h2. Late afternoon
29 1 Marc testing Mengel
30 18 Klaus Honscheid
# Before the 4pm meeting check with telops if SISPI instance and the GUIs were restarted.
31 14 Klaus Honscheid
# Ask telops to point telescope to white spot and fire afternoon calibration scripts
32 14 Klaus Honscheid
# Chair the 4pm meeting and present observing plan
33 1 Marc testing Mengel
# Edit the observing plan if needed
34 1 Marc testing Mengel
# Perform the Late Afternoon Checklist in the logbook
35 15 Thomas Diehl
# "Mark Exposures not to be processed"
36 11 Thomas Diehl
# "Implement the data quality":https://cdcvs.fnal.gov/redmine/projects/desops/wiki/DM_into_Database
37 5 Thomas Diehl
# Make sure observers are present and roles are defined/understood
38 1 Marc testing Mengel
39 5 Thomas Diehl
40 1 Marc testing Mengel
h2. Night
41 1 Marc testing Mengel
42 1 Marc testing Mengel
# Check that the dome flats finished ok
43 1 Marc testing Mengel
# Perform the Beginning of Night Checklist in the logbook
44 19 Thomas Diehl
# Write the Nightly Plan in the Shift Schedule page. The "Almanac" is kentools ephemeris.  
45 3 Thomas Diehl
# Keep the logbook 
46 7 Thomas Diehl
# Make sure the observers understand what they are doing
47 7 Thomas Diehl
# Make sure the observers get off to a good start
48 7 Thomas Diehl
# Be available to the observers if they have questions or problems
49 7 Thomas Diehl
# Try to get some sleep