Date User Activity Issue Comment Hours
10/14/2015 Jonathan Eisch Administration Task #10464: Get FNAL guidelines for HV pickoff/splitter Update on process from Geoff 1.00
10/13/2015 Jonathan Eisch Requirements Task #10464: Get FNAL guidelines for HV pickoff/splitter email to Geoff about FNAL design guidelines. 0.20
10/13/2015 Jonathan Eisch Implementation Task #10455: Test AC characteristics without HV network analyzer script to control function generator and oscilloscope 3.00
10/12/2015 Jonathan Eisch Testing Task #10456: Test HV resilliance up to 3kV test hv 0.20
    (1-4/4)