Maint-20130620
Last Modified {{last_modified}}

PLAN

PROGRESS

SERVICE DOWN UP COMMENT
Servers 08:50 11:20 kernel updates
Fermigrid 08:00 18:00 Fermigrid gatekeeper upgrades
SERVER DOWN UP COMMENT
minos25 10:44
minos27 09:20
minos50 09:20
minos51 11:20
minos52 09:35
minos53 11:20
minos54 09:35
minos-sam04 10:05
minos-slf5 08:50 08:55
minos-nearline 08:50 08:55

Issues after planned maintenance - none

  • Expected :
    • possibly remount /pnfs/minos
  • Pending
  • Fixed
    • mounted /pnfs/minos on minos25/54/-slf5
    • Fermigrid gateway limited throughput - pending INC000000390589
    • Got 120 pilots 07/22, still limited throughput
    • Fermigrid normal 07/23 afternoon ( glideinWMS condor upgraded )

Announcement to minos-users,minos-admin,minos-run,minosdb-support,ecl


Fermilab scheduled maintenance Thu 2013 Jul 18

The following Fermilab computing services will be down
on the scheduled Minos maintenance day this Thursday Jul 18 :

o All Minos server systems at Fermilab will have kernels upgraded.
o Fermigrid GPGrid gatekeeper upgrades - some jobs may restart.

As usual, see details and progress notes at
https://cdcvs.fnal.gov/redmine/projects/admin/wiki/Maint-20130718