Scheduled maintenance 2012 Jul 19 08:00 through 12:00

LAST MODIFIED {{last_modified}}

Planned maintenance COMPLETED

  • Kernel reboots ( to 2.6.18-308.8.2.el5 )
    • SLF5 - 2.6.18-308.11.1.el5 Release Date: Jul 18, 2012
    • SLF6 - 2.6.32-220.23.1.el6 Release Date: Jun 20, 2012
HOST FINISHED
ifora2 07:45
minos50 10:30
minos51 10:30
minos52 12:00
minos53 10:30
minos25 10:30
minos54 13:44
minos-sam02 10:30
minos-sam04 11:00
minos-mysql2 not scheduled for reboot
minos-slf5 11:15
  • Migration of the minos-db1 production database to a new host (tentative)
STARTED FINISHED
08:00 11:30

Issues after planned maintenance

  • Expected :
    • check /pnfs/minos mounts
      • Done - needed on most systems
    • restart mysql
      • Moot, done by DBA's
    • restart condor and GLideinWMS
      • dbox is restarting around 14:25
      • some cert's are expiring momentarily, he is working on this.
      • grid computing was restored at 15:20
  • Fixed :
  • Pending :