List from the 11.30 meeting today

1 Turn counters on and see if the PTB can take the rate
(Done)

2 complete 2nd cob reinstallation

3 wide drift window settings in config

4 plug penn trigger board in
(PTB trigger is in, and only trigger in, as of Mon Jan 11th - Tristan)

5 synchronisation tests

6 Counter voltage study 20h, not needed to be continuous 4h hunks are convenient.

7 Pedestal mode - PTB on very slow, take a long O(100ms) swath of unzero suppressed data) need to turn counter triggers off in config.

8 Calibration modes - discuss exactly what is needed and make configs

9 Second pedestal mode - random triggers with a normal millislice length, or pulser, but not aligned with 60Hz