Project

General

Profile

Issues

Filters

Apply Clear

# Project Tracker Status Priority Subject Assignee Updated
10468 ANNIE1-electronics-design Task Assigned Normal Pickoff/splitter enclosure production Jonathan Eisch 04/06/2016 11:13 PM
10463 ANNIE1-electronics-design Task Assigned Normal HV pickoff/splitter enclosure Jonathan Eisch 04/06/2016 11:13 PM
10461 ANNIE1-electronics-design Task Resolved Normal Full sized pickoff/splitter board population Jonathan Eisch 01/12/2016 03:07 PM
10457 ANNIE1-electronics-design Task Assigned Normal Design and build full sized pickoff/splitter board Jonathan Eisch 01/12/2016 03:07 PM
10456 ANNIE1-electronics-design Task Resolved Normal Test HV resilliance up to 3kV Jonathan Eisch 10/12/2015 02:40 PM
10449 ANNIE1-electronics-design Task Assigned Normal HV pickoff & signal splitter Jonathan Eisch 04/06/2016 11:14 PM
10443 ANNIE1-electronics-design Task Assigned Normal Make readout methods (to be used by artdaq) Jonathan Eisch 01/25/2018 07:16 AM
10442 ANNIE1-electronics-design Task Resolved Normal Throughput testing for ADC cards Jonathan Eisch 10/22/2015 01:40 PM
10440 ANNIE1-electronics-design Task Assigned Normal Externally trigger ADC cards Jonathan Eisch 01/25/2018 07:14 AM
9090 ANNIE1-electronics-design Feature Assigned Normal UC ADC user manual Jonathan Eisch 01/25/2018 07:14 AM
9089 ANNIE1-electronics-design Task Assigned Normal UC ADC cards Jonathan Eisch 01/25/2018 07:16 AM
9086 ANNIE1-electronics-design Task Assigned Normal Contact Zarko Pavlovic about beam timing signals. Jonathan Eisch 06/10/2015 10:48 AM
8913 ANNIE1-electronics-design Task Assigned Normal Send an ACDC + central card to QMUL Matthew Wetstein 10/09/2015 01:09 PM
8816 ANNIE1-electronics-design Milestone New Normal What is our calibration system? 01/25/2018 07:13 AM
8815 ANNIE1-electronics-design Task New Normal Final Decision on MRD and veto electronics 04/06/2016 11:08 PM
8813 ANNIE1-electronics-design Task Assigned Normal Design for clock distribution and timing Jonathan Eisch 01/25/2018 07:15 AM
8812 ANNIE1-electronics-design Task Assigned Normal Solidify Layout and number of crates channels for ANNIE RunI (Run II) Matthew Wetstein 04/06/2016 11:14 PM
8811 ANNIE1-electronics-design Task Resolved Normal Figure out the data rates and size of output from the system Jonathan Eisch 10/22/2015 01:38 PM
8809 ANNIE1-electronics-design Task Assigned Normal Interface for PSEC electronics with ART system Karen Hayrapetyan 10/09/2015 01:06 PM
8808 ANNIE1-electronics-design Task New Normal Get details of what we can get from the beam spill and timing Jonathan Eisch 06/10/2015 10:48 AM
8806 ANNIE1-electronics-design Milestone New Normal Redesign of LAPPD central card Matthew Wetstein 10/09/2015 02:12 PM
8628 ANNIE1-MCstudies Bug New Normal Optimization of acrylic volume 05/06/2015 09:43 AM
8627 ANNIE1-MCstudies Task New Normal SciBooNE driven calculation of skyshine rates 06/04/2015 10:33 AM
8625 ANNIE1-MCstudies Task New Normal Full MC model with 3D PMTs to study neutron tagging efficiencies 01/25/2018 07:24 AM
8623 ANNIE1-MCstudies Task New Normal Geant-based estimate of beam neutron rates and energies 01/25/2018 07:22 AM
11092 ANNIE1-mechanical-design Task New Normal Finish design of PMT holders 01/22/2016 08:51 AM
11076 ANNIE1-mechanical-design Task New Normal Final decision on liner specs and estimate 01/12/2016 02:33 AM
10203 ANNIE1-mechanical-design Task New Normal Determine placement of water pump Carrie McGivern 01/12/2016 02:33 AM
10201 ANNIE1-mechanical-design Task New Normal Determine how structure and top will be lowered in ANNIE Hall Carrie McGivern 01/19/2016 02:33 PM
10176 ANNIE1-mechanical-design Task New Normal Design of inner strcture Carrie McGivern 01/12/2016 02:31 AM
10175 ANNIE1-mechanical-design Task New Normal Design of access platform Carrie McGivern 12/06/2015 10:36 AM
10174 ANNIE1-mechanical-design Task New Normal Design of tank top Carrie McGivern 01/12/2016 02:32 AM
10173 ANNIE1-mechanical-design Task New Normal Cost out plastic bag liner, get lead time Matthew Wetstein 12/06/2015 10:33 AM
10171 ANNIE1-mechanical-design Task New Normal Follow up with Steve Dazeley Matthew Wetstein 09/18/2015 12:59 PM
10170 ANNIE1-mechanical-design Task New Normal Cost out PVC for ANNIE Run I Plan (with plan B) Carrie McGivern 01/12/2016 02:34 AM
8855 ANNIE1-mechanical-design Milestone New Normal Design of veto structure 08/05/2015 11:55 PM
8854 ANNIE1-mechanical-design Task New Normal Ship the muon veto structure 08/05/2015 11:47 PM
8853 ANNIE1-mechanical-design Task New Normal Water system shipped to FNAL for storage 12/06/2015 10:24 AM
8573 ANNIE1-mechanical-design Task New Normal Approval to purchase tank, from IA State Purchasing 05/27/2015 07:54 AM
8572 ANNIE1-mechanical-design Task New Urgent Fermilab approval for tank purchase 06/09/2015 02:01 AM
8618 ANNIE1-MRD-design Task New Normal Sign over stewardship of the MRD steel 06/05/2015 06:39 AM
8617 ANNIE1-MRD-design Task New Normal Follow up with NMSU about keeping the MRD Scintillator 12/18/2015 09:22 AM
8616 ANNIE1-MRD-design Task New Normal Follow up on Fermilab PMTs/Scintillator 06/09/2015 02:02 AM
8615 ANNIE1-MRD-design Task New Normal Arrange to get the Kansas/Syracuse PMTs and scintillator 06/05/2015 06:42 AM
8638 ANNIE1-Planning Milestone New Normal Complete TSW for ANNIE experiment 12/16/2015 11:56 PM
8630 ANNIE1-Planning Meeting New Normal ANNIE Run 1 Electronics Review 05/06/2015 09:47 AM
8629 ANNIE1-Planning Meeting New Normal Run 1 Mechanical Review 01/22/2016 08:51 AM
8575 ANNIE1-Planning Task New Normal Contact Stephen Geer about June PAC meeting 05/21/2015 10:07 AM
11100 ANNIE1-Staging Task New Normal Cables for Forward Veto 04/06/2016 11:09 PM
11091 ANNIE1-Staging Milestone New Normal Prototype PMT holder 04/06/2016 11:10 PM
(251-300/4596) Per page: 25, 50, 100, 5000

Also available in: Atom CSV PDF