# Project Tracker Status Priority Subject Assignee Updated
8662 VOMS Task Assigned Normal Evaluate current puppet module Nicholas Peregonow 07/02/2015 10:19 AM
8661 VOMS Task Accepted Normal Deploy VOMS3.fnal.gov Nicholas Peregonow 07/02/2015 10:19 AM
8636 ANNIE1-Commissioning Task New Normal Installation and commissioning of NCV 01/25/2018 07:11 AM
8634 ANNIE1-Staging Task New Normal Order materials for PMT structure 04/06/2016 11:09 PM
8633 ANNIE1-Staging Task New Normal MRD + veto system testing 04/06/2016 11:09 PM
8627 ANNIE1-MCstudies Task New Normal SciBooNE driven calculation of skyshine rates 06/04/2015 10:33 AM
8625 ANNIE1-MCstudies Task New Normal Full MC model with 3D PMTs to study neutron tagging efficiencies 01/25/2018 07:24 AM
8623 ANNIE1-MCstudies Task New Normal Geant-based estimate of beam neutron rates and energies 01/25/2018 07:22 AM
8618 ANNIE1-MRD-design Task New Normal Sign over stewardship of the MRD steel 06/05/2015 06:39 AM
8617 ANNIE1-MRD-design Task New Normal Follow up with NMSU about keeping the MRD Scintillator 12/18/2015 09:22 AM
8616 ANNIE1-MRD-design Task New Normal Follow up on Fermilab PMTs/Scintillator 06/09/2015 02:02 AM
8615 ANNIE1-MRD-design Task New Normal Arrange to get the Kansas/Syracuse PMTs and scintillator 06/05/2015 06:42 AM
8600 ANNIE1-Commissioning Task New Normal Dark commissioning of PMTs in ANNIE Hall (no water) 01/25/2018 07:10 AM
8599 ANNIE1-Commissioning Task New Normal Begin Run1 data taking 01/25/2018 07:11 AM
8577 ANNIE1-Assembly Task New Normal Water fill 01/25/2018 07:11 AM
8576 ANNIE1-Assembly Task New Normal Assembly and installation of PMT modules 04/06/2016 11:06 PM
8575 ANNIE1-Planning Task New Normal Contact Stephen Geer about June PAC meeting 05/21/2015 10:07 AM
8573 ANNIE1-mechanical-design Task New Normal Approval to purchase tank, from IA State Purchasing 05/27/2015 07:54 AM
8572 ANNIE1-mechanical-design Task New Urgent Fermilab approval for tank purchase 06/09/2015 02:01 AM
8521 Eroica Production Task New Normal Data Reco Stage 04/29/2015 10:30 AM
8520 Eroica Production Task New Normal MC Reco Stage 04/29/2015 10:30 AM
8519 Eroica Production Task New Normal MC Minos Stage 04/29/2015 10:30 AM
8518 Eroica Production Task New Normal MC Cal Stage 04/29/2015 10:30 AM
8517 Eroica Production Task New Normal MC Genie Stage 04/29/2015 10:01 AM
8516 Eroica Production Task New Normal Create Overlay Playlist 04/29/2015 10:30 AM