12556 Offline Production Operations Service Task Assigned Normal Communicate with the experiments the upcoming OPOS changes. Anna Mazzacane 05/06/2016 05:31 PM
12418 inst-bpm Task New Normal Boot flash for PXIE BPM test stand node John Diamond 04/29/2016 11:14 AM
12417 inst-bpm Task Assigned Normal Network connection and kerberos principles for PXIE BPM system John Diamond 04/29/2016 10:23 AM
12270 Recycler BPM Task Assigned Normal Build gbpm, rrbpm and rrtb code against MOOC 4.1. Elliott McCrory 04/22/2016 02:24 PM
12272 Recycler BPM Task New Normal Deploy MOOC 4.1 to a single rbpm house and verify Elliott McCrory 04/22/2016 02:22 PM
12271 Recycler BPM Task New Normal Deploy MOOC 4.1 to test stand and verify Elliott McCrory 04/22/2016 02:22 PM
12353 VME Intensity Monitor Task Assigned Normal Rename ANUB John Diamond 04/21/2016 10:46 AM
11804 CMS dCache Task Resolved Normal Down time 2016-02-04 for glibc update (HUANG) Chih-Hao Huang 04/08/2016 01:53 PM
12147 CMS dCache Task Resolved Normal Handling cmsstor437 / cmsdisk437438 issue Chih-Hao Huang 04/08/2016 01:52 PM
8812 ANNIE1-electronics-design Task Assigned Normal Solidify Layout and number of crates channels for ANNIE RunI (Run II) Matthew Wetstein 04/06/2016 11:14 PM
10449 ANNIE1-electronics-design Task Assigned Normal HV pickoff & signal splitter Jonathan Eisch 04/06/2016 11:14 PM
10512 ANNIE1-electronics-design Task New Normal Test final pickoff/splitter 04/06/2016 11:14 PM
10463 ANNIE1-electronics-design Task Assigned Normal HV pickoff/splitter enclosure Jonathan Eisch 04/06/2016 11:13 PM
10468 ANNIE1-electronics-design Task Assigned Normal Pickoff/splitter enclosure production Jonathan Eisch 04/06/2016 11:13 PM
10509 ANNIE1-electronics-design Task Assigned Normal Attach bulkhead connectors and pcb mounting hardware Jonathan Eisch 04/06/2016 11:13 PM
11082 ANNIE1-Assembly Task New Normal Access Platform: construction and installation 04/06/2016 11:11 PM
8634 ANNIE1-Staging Task New Normal Order materials for PMT structure 04/06/2016 11:09 PM
11100 ANNIE1-Staging Task New Normal Cables for Forward Veto 04/06/2016 11:09 PM
8633 ANNIE1-Staging Task New Normal MRD + veto system testing 04/06/2016 11:09 PM
10510 ANNIE1-electronics-design Task Assigned Normal Mount pickoff/splitter pcb in enclosure, solder wires to bulkhead connectors Jonathan Eisch 04/06/2016 11:09 PM
8815 ANNIE1-electronics-design Task New Normal Final Decision on MRD and veto electronics 04/06/2016 11:08 PM
11099 ANNIE1-Assembly Task New Normal Installation of Forward Veto Cabling 04/06/2016 11:07 PM
11084 ANNIE1-Assembly Task New Normal Construction of NCV 04/06/2016 11:07 PM
11081 ANNIE1-Assembly Task New Normal Practice lower inner structure into tank 04/06/2016 11:06 PM
8576 ANNIE1-Assembly Task New Normal Assembly and installation of PMT modules 04/06/2016 11:06 PM
(4276-4300/4650) Per page: 25, 50, 100, 5000