Schedule a site-wide GUMS downtime of 1h

Added by Anthony Tiradani almost 5 years ago. Updated almost 5 years ago.

Status:
Closed
Priority:
Normal
Assignee:
Start date:
08/20/2015
Due date:
08/20/2015
% Done:

100%

Estimated time:
2.00 h
Spent time:
Duration: 1

Description

Schedule site-wide GUMS downtime of 1h. The actual downtime will be shorter. The impact may be minimal since dcache (gplazma) has caching built in.

History

#1 Updated by Merina Albert almost 5 years ago

Gerard has notified FIF and scheduled on Aug 20th. Will make sure talk with Neha

#2 Updated by Merina Albert almost 5 years ago

  • Due date set to 08/20/2015
  • Status changed from New to Closed
  • Start date changed from 07/22/2015 to 08/20/2015
  • % Done changed from 0 to 100
  • Estimated time set to 2.00 h

migration completed