Necessary Maintenance #8722
Load-balance current draw from sebs in DAQ room at LArTF
Start date:
05/12/2015
Due date:
% Done:
0%
Estimated time:
Description
An additional PDU and UPS were purchased to distribute the load from the SEBs in the first readout rack in the DAQ room at LArTF. The PDU has been temporarily installed and half of the power supplies that were connect to one of the two PDUs that were already installed were moved to it. The UPS now needs to be installed and the loads distributed according to the operating ranges of the PDUs and UPSs.