Milestone #8571

Tank Manufacture

Added by Matthew Wetstein over 4 years ago. Updated almost 4 years ago.

Status:
New
Priority:
High
Assignee:
-
Start date:
06/01/2015
Due date:
08/24/2015
% Done:

100%

Estimated time:
Duration: 85

Related issues

Related to ANNIE1-mechanical-design - Task #8572: Fermilab approval for tank purchaseNew05/04/201505/29/2015

Related to ANNIE1-mechanical-design - Task #8573: Approval to purchase tank, from IA State PurchasingNew05/04/201505/29/2015

History

#1 Updated by Matthew Wetstein over 4 years ago

  • Related to Task #8572: Fermilab approval for tank purchase added

#2 Updated by Matthew Wetstein over 4 years ago

  • Related to Task #8573: Approval to purchase tank, from IA State Purchasing added

#3 Updated by Matthew Wetstein over 4 years ago

  • % Done changed from 0 to 20

#4 Updated by Matthew Wetstein over 4 years ago

  • % Done changed from 20 to 40

#5 Updated by Matthew Wetstein about 4 years ago

  • % Done changed from 40 to 60

#6 Updated by Matthew Wetstein about 4 years ago

  • % Done changed from 60 to 80

#7 Updated by Matthew Wetstein almost 4 years ago

  • % Done changed from 80 to 100