Task #24603
New Chassis for MILLRF - RF filters and other loose components in MI
Start date:
07/07/2020
Due date:
% Done:
0%
Estimated time:
Description
There are several filters and other connectorized parts sitting in the MI LLRF VXI crate that need to be placed into a chassis. Also, the cabling continues to be a mess and some thought needs to go into this.
This will have to be requested as shutdown work.
Dan, will be assigned to build the chassis and help with the cable plant.