Description

The resonance control system for the HWR cavities will be first driven by the Euro-Crate based slow tuner
hardware from Argonne. Testing and simulations of the slow tuner have helped to develop a path to the tuner
control system driven directly by the LLRF controller card along with a signal conditioning card to match up the
controller and transducer voltage levels. Some questions regarding the Argonne slow tuner hardware need to be clarified.
The test/simulation results and questions to be resolved are included in one document. An architecture for the initial
and final stages for the Resonance Control System are also shown. The signal conditioning chassis will also house
a power-supply for the valves/transducer and all the appropriate connectors to make the connections for both
stages of operation. A separate drawing for the signal conditioning chassis is being prepared.

HWR_Eurocrate_Tuner_Questions.docx (252 KB) HWR_Eurocrate_Tuner_Questions.docx Philip Varghese, 01/27/2020 07:08 PM
HWR_ResonanceControl_Stage1.pdf (58.8 KB) HWR_ResonanceControl_Stage1.pdf Philip Varghese, 01/27/2020 07:10 PM
HWR_ResonanceControl_Stage2.pdf (74.5 KB) HWR_ResonanceControl_Stage2.pdf Philip Varghese, 01/27/2020 07:10 PM
Wiring diagram stage 1.pdf (28 KB) Wiring diagram stage 1.pdf Daniel Klepec, 01/29/2020 11:50 AM
HWR_Stage1_HardwareTesting.docx (163 KB) HWR_Stage1_HardwareTesting.docx Philip Varghese, 02/06/2020 12:16 PM
HWR_Stage1_HardwareTesting.docx (163 KB) HWR_Stage1_HardwareTesting.docx Philip Varghese, 02/10/2020 03:18 PM
Wiring diagram stage 1.pdf (63.2 KB) Wiring diagram stage 1.pdf Daniel Klepec, 02/12/2020 11:17 AM
HWR_Stage1_HardwareTesting2.docx (300 KB) HWR_Stage1_HardwareTesting2.docx Philip Varghese, 02/16/2020 11:05 PM

History

#1 Updated by Daniel Klepec 2 months ago

Signal Conditioning Chassis stage 1 drawing is enclosed.

#2 Updated by Philip Varghese about 2 months ago

Re-entering update from 2/6. File got deleted inexplicably.

2/6 update said:

One channel of the Eurocrate slow tuner hardware was tested with a signal conditioning/connector junction box and the
LLRF controller. Initial Results of the open loop testing are shown.

#3 Updated by Daniel Klepec about 2 months ago

Updated wiring diagram of the Signal Conditioning Chassis is attached.

#4 Updated by Philip Varghese about 2 months ago

Measurements were made with the Pressure and Vacuum valves and the pressure transducer of the
HWR slow tuner system at CMTF to characterize their power and control input requirements.
Timing and control measurements of the pressure regulation loop of the slow tuner eurocrate
controller are also shown.