Assist in the setup of the DUNE cold electronics teststand at PAB

Added by Kurt Biery 11 months ago. Updated 9 months ago.

Status:
Work in progress
Priority:
Low
Assignee:
-
Category:
-
Target version:
-
Start date:
08/15/2018
Due date:
% Done:

80%

Estimated time:
Experiment:
-
Co-Assignees:
Duration:

History

#1 Updated by John Freeman 9 months ago

  • Status changed from New to Work in progress
  • % Done changed from 0 to 80

We've gotten to a point where as of Oct. 7, two RCEs (cob1_rce01 and cob1_rce04) were successfully run on. Also, to quote Matt Graham from an email he sent yesterday:

"From the DAQ side, the hardware (RCEs and timing) is all there and working. I tested sending RCE-emulated data to the back end via artDAQ and it seems to have worked.

I think the WIB will be ready to send data to the RCEs soon, once the timing to that is sorted out (they were working on it today)."