Finalize design and layout of water system

Added by Matthew Wetstein almost 2 years ago. Updated almost 2 years ago.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
01/01/2018
Due date:
05/01/2018
% Done:

70%

Estimated time:
Duration: 121

History

#1 Updated by Matthew Wetstein almost 2 years ago

  • % Done changed from 30 to 100

#2 Updated by Matthew Wetstein almost 2 years ago

  • % Done changed from 100 to 70