Project

General

Profile

Task #18571

Finalize design and layout of water system

Added by Matthew Wetstein over 1 year ago. Updated over 1 year ago.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
01/01/2018
Due date:
05/01/2018
% Done:

70%

Estimated time:
Duration: 121

History

#1 Updated by Matthew Wetstein over 1 year ago

  • % Done changed from 30 to 100

#2 Updated by Matthew Wetstein over 1 year ago

  • % Done changed from 100 to 70


Also available in: Atom PDF