Support #15792: Individual Minos SLF5 node shutdowns

minos50 retirement

Added by Arthur Kreymer over 3 years ago. Updated about 3 years ago.

Status:
Closed
Priority:
High
Start date:
03/08/2017
Due date:
03/31/2017
% Done:

100%

Estimated time:
10.00 h
Duration: 24

Description

Retire minos50 by 2017 Apr 01

History

#1 Updated by Arthur Kreymer over 3 years ago

  • Status changed from Accepted to Assigned

#2 Updated by Arthur Kreymer over 3 years ago

  • Status changed from Assigned to Work in progress
  • % Done changed from 0 to 10

#3 Updated by Arthur Kreymer over 3 years ago

  • % Done changed from 10 to 20

Summary

Task Completed Comment
Ganglia 03/21 idle from 02/24
procsum 03/21 idle from 03/18, asousa idle 03/20
opt 03/20 nothing needed
home 03/20 nothing needed
scratch 03/21 archived

Ganglia averages
Idle 99/6%
Load 1 55m
Net in 38k
Net out 272k ( archiving scratch )

#4 Updated by Arthur Kreymer over 3 years ago

  • % Done changed from 20 to 80

RITM0542037 3/22 minos50 shutdown

At your convenience, please shut down the minos50 system.
This SLF5 system is being retired.

See preparation details in https://cdcvs.fnal.gov/redmine/issues/15797

Please hold the hardware for a month before disposal,
in case we overlooked something.
_________________________________________________________________

2017-03-22 10:46:47 CDT - Christophe Bonnaud (Additional comments)
 
minos50 has been shut down.

#5 Updated by Arthur Kreymer over 3 years ago

  • % Done changed from 80 to 90

#6 Updated by Arthur Kreymer over 3 years ago

  • % Done changed from 90 to 100

#7 Updated by Arthur Kreymer over 3 years ago

  • Status changed from Work in progress to Resolved

#8 Updated by Arthur Kreymer about 3 years ago

  • Status changed from Resolved to Closed