Project

General

Profile

Task #13425

Milestone #13399: Parent reconstruction milestones/tasks for reconstruction necessary for MCC8 and reconstruction "v6"

Milestone #13400: MCC8 and "v6" reconstruction development

Milestone #13405: Shower Reconstruction

Shower Reconstruction - OpenCV tasks

Added by Tracy Usher about 3 years ago. Updated about 3 years ago.

Status:
New
Priority:
Normal
Target version:
-
Start date:
08/23/2016
Due date:
% Done:

43%

Estimated time:
(Total: 0.00 h)
Duration:

Description

This is parent task for the OpenCV elements of shower reconstruction that need to be developed or refined


Subtasks

Task #13633: Remove external shower-reconstruction dependencyAssigned

Task #13634: Overlapping track removalAssigned

Task #13747: Pi0 ClusteringNew

History

#1 Updated by Tracy Usher about 3 years ago

  • Parent task set to #13405