Project

General

Profile

Task #11479

Milestone #11262: March production reconstruction

Milestone #11237: Develop / optimize signal processing algorithms needed for production processing

Restructure existing hit finding algorithm for maintainability

Added by Erica Snider almost 5 years ago. Updated over 4 years ago.

Status:
Closed
Priority:
Normal
Assignee:
Target version:
-
Start date:
01/22/2016
Due date:
01/29/2016
% Done:

100%

Estimated time:
Duration: 8

History

#1 Updated by Erica Snider almost 5 years ago

  • % Done changed from 50 to 100

Completed along with parameter optimization work

#2 Updated by Tracy Usher over 4 years ago

  • Status changed from New to Resolved

This task has been completed for the purposes of Neutrino 16

#3 Updated by Tracy Usher over 4 years ago

  • Status changed from Resolved to Closed

This task considered complete for Neutrino 16