Project

General

Profile

Task #11478

Milestone #11262: March production reconstruction

Milestone #11237: Develop / optimize signal processing algorithms needed for production processing

Integrate event-by-event channel status into uB implementation of ChannelStatus service

Added by Erica Snider almost 4 years ago. Updated over 3 years ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Target version:
-
Start date:
01/22/2016
Due date:
02/15/2016
% Done:

0%

Estimated time:
Duration: 25

History

#1 Updated by Erica Snider almost 4 years ago

  • Due date set to 02/15/2016
  • Parent task set to #11237

#2 Updated by Erica Snider almost 4 years ago

  • Status changed from New to Remission

This is linked to 11477, which is deferred until after the March 1 production

#3 Updated by Tracy Usher over 3 years ago

  • Status changed from Remission to Closed

This task considered complete for Neutrino 16