Order rack enclosure

Added by Jonathan Eisch almost 4 years ago. Updated almost 4 years ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Start date:
10/21/2015
Due date:
01/08/2016
% Done:

100%

Estimated time:
Duration: 80

Description

We may modify an off-the-shelf 1u or 2u rack enclosure for each pickoff/splitter box.

History

#1 Updated by Jonathan Eisch almost 4 years ago

  • Due date changed from 10/26/2015 to 01/08/2016
  • Status changed from New to Accepted
  • % Done changed from 0 to 50

Enclosures delivered to ISU.
Drawings have been updated.

#2 Updated by Jonathan Eisch almost 4 years ago

  • % Done changed from 50 to 100

#3 Updated by Jonathan Eisch almost 4 years ago

  • Status changed from Accepted to Closed