Zarko, Tia, Corey, Tom, Keith, Carrie, David, Jason

Booster: Bill gone
BNB: Beamline is running fine
Booster Saftey for More Protons: Shielding studies were approved. Need to take out some beamline instrumentation and put up new safety signs.
Horn4: ready to test soon, plan on substation power switch (9 days-ish)
MicroBooNE CRT
ANNIE: flakey cables from crates to laptops. 
MicroBooNE: server problems, detector ok, no impact on uptime.
MiniBooNE: Beam DAQ machine nearing end of life on SL5, but main DAQ is firewalled and safe, try to get that for the Beam DAQ. Other machines can up updated. MiniBooNE analysis machines are also old, will meet with Scientific Computing.